The Regulatory Track

No 765 Line, Inc. · A Wisconsin 501(c)(3) · Sourced. Coordinated.
Wisconsin PSC permit case · expected fall 2026

Resources › PSC · Regulatory

PSC · Regulatory

The regulatory track.

The Wisconsin Public Service Commission decides whether the 765 kV line gets a permit — on the strength of a written record. This track is about that record: how it gets built, how the public takes part, and the documents inside it. (The local-government work lives on a separate track.)

How the public takes part

The Commission decides on a record — written filings, sworn expert testimony, studies, and public comment. The work to shape that record happens while the docket is open, not after the vote. There are two main ways the public participates:

  • Public comment. Once the application is filed, anyone can submit a comment to the Commission. Comments become part of the public record the Commission reviews.
  • Intervention. An intervenor is a person or group the Commission admits as a formal party to the docket — able to file testimony, present evidence, and cross-examine. Qualifying parties may petition the Commission to intervene.

For the proposed 765 kV line, the application is expected to be filed at the Wisconsin PSC in fall 2026. Until it is filed, there is no docket to comment in or intervene in. When the docket opens, the specifics — case number, deadlines, and how to file — will be posted here.

Source · Wisconsin PSC CPCN process; campaign timeline
Why the record matters

MISO’s planning case claims the line returns $1.80 to $3.50 of benefit for every dollar spent. MISO’s own Independent Market Monitor estimates less than 40¢ per dollar. That gap is the kind of question the record exists to resolve — and where public comment and intervenor testimony carry weight.

See the benefit case →